Route 49 La Barr Meadows Widening |
Description: Near the city of Grass Valley, from 0.7 mile north of Alta Sierra Drive to 0.5 mile south of Wellswood Way. Widen to 4-lane highway with continuous median lane.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Nevada |
City | |
Zip Code | 95949 |
Senate District |
04 |
Assembly District | 03 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | Nevada 49 |
Postmile Begin/End | 9.7 R 11.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 38 | |
Lane Miles Added (Mixed) | 2.8 | 2.8 |
Peak Period Time Savings (minutes) | 2559 | 2760 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Sergio Aceves | (530) 741-5120 | sergio.aceves@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Sergio Aceves | (530) 741-5120 | sergio.aceves@dot.ca.gov | |
Right of Way Phase |
Caltrans | Sergio Aceves | (530) 741-5120 | sergio.aceves@dot.ca.gov | |
Construction Phase |
Caltrans | Sergio Aceves | (530) 741-5120 | sergio.aceves@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Jeff Pulverman | (530) 741-4337 | jeff.pulverman@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $3,125 | $3,125 | ||||
IIP Augmentation |
$0 | $3,125 | $3,125 | ||||
CMIA |
$18,568 | $-10,343 | $8,225 | ||||
Non-bond Funding | |||||||
State/Federal* |
$21,932 | $-6,388 | $15,544 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $40,500 | $-10,481 | $30,019 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$3,500 | $-600 | $2,900 | $2,852 | |||
Design(PS&E) |
$2,000 | $672 | $2,672 | $2,810 | |||
Right of Way |
$10,500 | $0 | $10,500 | $9,711 | |||
Construction |
$24,500 | $-10,553 | $13,947 | $13,444 | |||
Total* | $40,500 | $-10,481 | $30,019 | $28,817 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2000 10/01/2007 |
|
01/01/2000 10/01/2007 |
100 | 01/01/2000 10/01/2007 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 01/01/2009 |
|
07/01/2007 05/15/2009 |
100 | 07/01/2007 05/05/2009 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2008 10/01/2009 |
|
01/01/2008 10/01/2009 |
100 | 05/30/2007 10/01/2009 |
7 0 |
|
Begin Construction Phase
End Construction Phase |
05/01/2009 06/01/2012 |
|
06/01/2010 12/01/2014 |
100 | 05/28/2010 04/08/2014 |
0 8 |
|
Begin Closeout Phase
End Closeout Phase |
06/01/2013 06/01/2014 |
|
12/01/2014 12/01/2016 |
50 | 04/08/2014 10/14/2019 |
8 -35 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 03/01/2009 | 03/01/2009 | 0 | 0 | |||
Implementation Date | 07/01/2010 | 07/01/2010 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 38 | |
Lane Miles Added (Mixed) | 2.8 | 2.8 |
Peak Period Time Savings (minutes) | 2559 | 2760 |
Bond Funding Cost | |
---|---|
Adopted: |
$18,568,000 |
Current Approved: |
$8,225,000 |
Actual Expenditures: |
$8,225,000 |
Status as of December 31, 2023.