Route 49 La Barr Meadows Widening

Description: Near the city of Grass Valley, from 0.7 mile north of Alta Sierra Drive to 0.5 mile south of Wellswood Way. Widen to 4-lane highway with continuous median lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Nevada
City
Zip Code 95949
 
Senate District
04
Assembly District 03
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Nevada 49
Postmile Begin/End 9.7 R  11.2
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  38      
Lane Miles Added (Mixed)  2.8    2.8  
Peak Period Time Savings (minutes)  2559    2760  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Sergio Aceves (530) 741-5120   sergio.aceves@dot.ca.gov
Design (PS&E) Phase
Caltrans Sergio Aceves (530) 741-5120   sergio.aceves@dot.ca.gov
Right of Way Phase
Caltrans Sergio Aceves (530) 741-5120   sergio.aceves@dot.ca.gov
Construction Phase
Caltrans Sergio Aceves (530) 741-5120   sergio.aceves@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jeff Pulverman (530) 741-4337   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $3,125 $3,125
IIP Augmentation
$0 $3,125 $3,125
CMIA
$18,568 $-10,343 $8,225
Non-bond Funding
State/Federal*
$21,932 $-6,388 $15,544
Non Budgeted ETC
$0 $0 $0
 
Total**** $40,500 $-10,481 $30,019

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,500 $-600 $2,900 $2,852
Design(PS&E)
$2,000 $672 $2,672 $2,810
Right of Way
$10,500 $0 $10,500 $9,711
Construction
$24,500 $-10,553 $13,947 $13,444
 
Total* $40,500 $-10,481 $30,019 $28,817

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2000 

10/01/2007 
 

 
01/01/2000 

10/01/2007 
100  01/01/2000 

10/01/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

01/01/2009 
 

 
07/01/2007 

05/15/2009 
100  07/01/2007 

05/05/2009 


Begin Right of Way Phase

End Right of Way Phase
01/01/2008 

10/01/2009 
 

 
01/01/2008 

10/01/2009 
100  05/30/2007 

10/01/2009 


Begin Construction Phase

End Construction Phase
05/01/2009 

06/01/2012 
 

 
06/01/2010 

12/01/2014 
100  05/28/2010 

04/08/2014 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

06/01/2014 
 

 
12/01/2014 

12/01/2016 
50  04/08/2014 

10/14/2019 


-35 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009   
Implementation Date 07/01/2010    07/01/2010   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 38
Lane Miles Added (Mixed) 2.8 2.8
Peak Period Time Savings (minutes) 2559 2760

Bond Funding Cost
Adopted:
$18,568,000
Current Approved:
$8,225,000
Actual Expenditures:
$8,225,000

 

Status as of December 31, 2023.